Lights and Plaster
During the last couple of days the sparkies have been back to move some downlights, and the plasterer has been repairing the holes.
We are now waiting on the painter, roof tiler, interior tiler and some odds and ends to be sorted before we can do a handover. One of the problems we have is weather related - the tiler can't do the balcony tiles until this darn rain stops! No firm date for handover - but we are working towards Monday the 28th July.
A couple of people have asked why the lights had to be changed - when we planned our lights we gave some careful consideration to where we wanted the lights, especially over the kitchen work area. In practical terms, the lights could not be placed exactly where we had them on the plan, as the heating and cooling ducts were larger than shown on the plan - the sparkie had to make some changes, but we were not happy with the lighting of the bench.
Having said that, we are very happy with the new arrangement.
Having said that, we are very happy with the new arrangement.
Labels: down lights, electricals, Garage, plaster

subscribe via email
Atom feed
3 Comments:
Hi B & P
Wow you are so close to being finished! You are sooooo lucky. It is looking fantastic.
23 July 2008 17:36
La la la la la laa ....
Just doing some vocal exercises in preparation .... it's almost over and I'm ready to sing!!!!!!!!
Happy to have the rain sent our way to give you some clear days .. if you could just arrange that please, that would be great! :-)
24 July 2008 08:02
Hi perry
You are very close now, it may drag on a bit, as the tradies have to come back to rectify your issues. Make sure, before accepting handover you are completely happy & satisfied, if not dont accept handover.
We had 5 pages on our PCI forms plus a few extra, all were fixed before we accepted handover.
All the best,
Chat soon
Andy
24 July 2008 16:08