Our Cremorne 41 Timeline
The progress list was getting a bit too big to keep on the main page, so here it is!
- 22/07/08 - Plasterers finish pathcing holes etc.
- 21/07/08 - Sparkies finish their outstanding items
- 18/07/08 - Practical Completion Inspection
- 16/07/08 - Render finished
- 14/07/08 - Flyscreens installed
- 11/07/08 - More painting
- 09/07/08 - Site cleaned
- 08/07/08 - Heater installed
- 06/07/08 - House cleaned
- 04/07/08 - New locks fitted
- 03/07/08 - Garage door installed
- 30/06/08 - Garage fix, and balcony fix completed
- 27/06/08 - Ducted vac plates installed
- 26/06/08 - Render started
- 24/06/08 - Internal door handles installed
- 23/06/08 - Glass splashbacks installed
- 23/06/08 - Shower screens installed
- 21/06/08 - Taps and toilets installed
- 17/06/08 - Grouting of tiles
- 16/06/08 - Tiling continued
- 14/06/08 - Carpentry above garage door
- 13/06/08 - Retaining Wall Constructed
- 09/06/08 - Vanity Raised to correct height
- 29/05/08 - Stormwater and Sewer Connected
- 28/05/08 - Tiling started
- 27/05/08 - Electrical fit-off
- 26/05/08 - Garage ceiling plaster installed
- 24/05/08 -
Downpipes installed
- 23/05/08 -
Benchtops installed
- 22/05/08 - Stairs
Stained
- 21/05/08 - Phone
line terminated
- 19/05/08 - Roof
tiling complete
- 14/05/08 - Sealer
applied
- 12/05/08 - Plaster
issues fixed
- 10/05/08 -
Brickwork complete
- 10/05/08 - Fix
complete
- 09/05/08 - Plaster
Inspected
- 09/05/08 - Interior
Painting Starts
- 07/05/08 - Cabinets
Installed
- 07/05/08 - Plaster
complete
- 07/05/08 - Fix
mostly complete
- 02/05/08 - Garage
Trusses up
- 02/05/08 - Balcony
Framed
- 02/05/08 - Cabinets
Delivered
- 01/05/08 - Cornice
happening
- 30/04/08 - Fix
started
- 28/04/08 - Stairs
in!
- 24/04/08 - Exterior
Painting started
- 23/04/08 - Stairs
delivered
- 21/04/08 - Eaves
lined
- 19/04/08 - Rear
Cladding Installed
- 17/04/08 - Bricks
Cleaned
- 15/04/08 - Bricks
Done
- 11/04/08 - Plaster
Sheets Up
- 09/04/08 - Brickies
Back!
- 07/04/08 - Plaster
Started
- 06/04/08 -
Bulkheads Installed
- 05/04/08 -
Bulkheads Delivered
- 04/04/08 - Plaster
Delivered
- 02/04/08 - Wall
insulation
- 01/04/08 - Frame
Inspection
- 29/03/08 - Lockup
started
- 29/03/08 - Sound
Insulation started
- 28/03/08 -
Electricals Installed
- 28/03/08 - Alarm
Cabling Installed
- 28/03/08 - Upper
Floor wrapped
- 26/03/08 - Upper
Windows in
- 25/03/08 - Plumbing
installed
- 25/03/08 -
Scaffolding Erected
- 20/03/08 - Ducted
cooling installed
- 12/03/08 -
Brickwork Started
- 12/03/08 - We have
a roof!
- 07/03/08 - Roof
Tiles delivered
- 07/03/08 - Bricks
delivered
- 06/03/08 - Lower
floor sarking
- 04/03/08 - Plumbing
done
- 01/03/08 - Frame
Completed
- 26/02/08 - 2nd
Storey started
- 21/08/08 - First
frame bits up
- 18/02/08 - Slab
pumped!
- 16/02/08 - Waffle
pods installed
- 15/02/08 - Slab
formwork done
- 14/02/08 - Slab
Plumbing installed
- 13/02/08 - Tap and
Piers installed
- 11/02/08 - Site
filled and shaped
- 08/02/08 - Site
scraped
- 31/01/08 - File
goes to Construction