Hi! Welcome to our Porter Davis Cremorne 41. This site will follow the progress of our home from the start, through every stage until the end. We will try and include as many photos as we can along the way. Why do you care? You probably don't - unless you are building or thinking of building your own place, or unless you are one of our friends or relatives. Strap yourself in - it's going to be a long and bumpy ride!

Sunday, 20 April 2008

Extra Pictures

Today we went to the house and took a few extra pictures. Bernadette decided that it was time to do a bit of a clean through - some of the tradies who had been through had a thing for fast food, and there was rubbish all over the place.



Rear cladding looks great!


Bath has been delivered - we went for the longer 1700mm one - standard is around 1500mm.


Ummm. A stack of bricks.


Lining the overhangs of the alfresco.




After the cleanup!


Magpies. There seems to be a lot of these bird hanging around the site. I counted 20 of them yesterday. During the week the reason became clear - one of the local residents feeds them every day. As a result, every black roof in the area has bird crap all over it where maggies sit on the tv anetenna. They never leave, because they get a free meal every day!

Labels: , , , ,

Saturday, 19 April 2008

Closer and closer

If you read the title, you might wonder... closer and closer to what?

Answer: Lockup, and the next big invoice from Porter Davis.

Today the plasterer and chippie were on site, along with the friendly neighborhood brick stacker.

Plaster is making good progress, as can be seen below. The upstairs fill work has been done, and the downstairs is in progress. After that, it's the cornices on both levels.







Speaking to the Site Supervisor (who also visited the site today), it looks like the staircase isn't too far away. The scaffolding will be coming down soon, and a site clean will then happen which should transform the look of the house.

The rear cladding was installed today - the photo below was taken while in progress. We will upload a completed photo tomorrow.


Some of the eave lining has also been done (the fiddly bits at the back of the house) and the front eave lining will happen tomorrow or Monday.

Our bath as also been delivered. No photo... we really didn't take enough photos today.... something to do with moving a couple of packs of bricks!